A laundromat is a shop full of water, gas, heat and noise, so councils and water authorities take an interest. Most new laundromats need more than one approval before the fit-out starts. The rules differ by state and by council, so treat this as a checklist of questions, not the answers for your site.
1. Check the zoning before you sign a lease
Ask the council's planning team whether a laundromat is allowed at that address, and what approval it needs. If the shop was a laundromat before, or another use the planning rules treat the same way, the path can be short. If it was a café, an office or a warehouse, the change of use may need a development application. A town planner can answer this quickly if the council can't.
Ask too about trading hours. A 24-hour laundromat near homes can draw conditions about noise from dryer exhausts and people coming and going late at night.
2. Make the lease subject to approvals
Ask your solicitor to make the lease conditional on getting the approvals you need, and on the landlord agreeing to the fit-out works: drainage, dryer ducting through the roof or wall, gas and power upgrades. Without that, you can end up paying rent on a shop you can't use.
3. Draw the layout
Every application that follows needs a drawing of the shop with the machines in it. The laundromat builder gives you a concept layout with real Fagor machine sizes and a services list, and we turn it into drawings for the landlord and trades once the site is measured.
4. Planning approval
Where a development application is needed, the council will usually want the layout, the hours, the signage and how waste, noise and parking are handled. Some areas have a faster approval path for a simple change of use; others need the full application. Allow time for it in your plan, because the fit-out normally can't start until it's approved.
5. Trade waste approval
Washers send lint, detergent and warm water to the sewer, so most laundromats need a trade waste approval from the local water authority, often with a lint trap on the drain. Apply early. If you're buying an existing laundromat, check the approval is in place and can be transferred to you. See what a laundromat site needs.
6. Building approval for the fit-out
New drains, ducting, walls and plumbing may need a building or construction approval and inspections, depending on the work and your state. A building certifier can tell you what applies.
7. Licensed trades and their certificates
Gas, electrical and most plumbing work must be done by licensed trades, and each one issues a compliance certificate when the work is done. Keep them together: the council, the landlord, your insurer and a future buyer may all ask for them.
8. Signage
Many councils need an approval for signs on the shopfront or above the awning. Include them in the planning application if you can, rather than applying again later.
Where we help
We draw the layout, list the power, gas, water and drain connection for every machine, check the site's services, and work with your trades through the fit-out. Our My Laundromat site explains how a laundromat fit-out works. Start with the free laundromat builder, or call 1300 70 69 70 to talk about your site.